Sim-Ex™ Practice Exams for PMP Practice Questions

Home     Next

Q1. Tim, the new project manager of US based developer company has very little project management experience, but he has been assigned as the project manager of a new skyscrapers project. Because he is working in a matrix organization to complete his project, he can expect communication to be:

A. Open and accurate

B. Hard to automate

C. Complex

D. Simple

Correct Answer: C

Explanation:

In a matrix organization, the communication is expected to be complex. Hard to automate in some cases right, but is not a general characteristic of matrix organization. So, Complex is the obvious choice. In Projectized organization it can be simple.

Domain Name: 1-3. Foundational
Reference: PMBOK5 Section 2.1 Page 21

Home     Next


Disclaimer: Simulationexams.com is not affiliated with any certification vendor, and Sim-Ex™ Practice Exams are written independently by SimulationExams.com and not affiliated or authorized by respective certification providers. Sim-Ex™ is a trade mark of SimulationExams.com or entity representing Simulationexams.com.PMP® is a trademark of PMI™.