Q5. Estimate activity resource is the process of eliminating the time and quantities of materials, people, equipment or suppliers required to perform each activity. Which of the below statement don't comply with estimate activity resource process?
A. As more precise information about the project become available, the contingency reserve may be reduced or used.
B. Resource calendar includes consideration of attributes such as resource calendar and skill level as well as various geographical locations from which resource initiate and when it may be available
C. Estimate activity resource process is closely coordinated with estimate cost process
D. While working on Estimate activity resource we should not look to see how leads and lags affect the time estimate
Correct Answer:A
Explanation:
The more precise information about the project become available, the contingency reserve may be reduced or used. But look at the question again, it asks about estimate activity resource not develop schedule process.
Domain Name: 6. Time
Reference: PMBOK5 Section 6.4 Page 163
Disclaimer: Simulationexams.com is not affiliated with any certification vendor, and Sim-Ex™ Practice Exams are written independently by SimulationExams.com and not affiliated or authorized by respective certification providers. Sim-Ex™ is a trade mark of SimulationExams.com or entity representing Simulationexams.com.PMP® is a trademark of PMI™.