Q8. Perform quality assurance process uses data from quality measurements to track the way we work and improve it all the time. Which of the below statements is incorrect about quality assurance?

A. During project planning quality assurance measures how long it takes to plan the project or measure other areas of planning performance

B. The quality assurance process reviews the quality measurement plan and uses the measurements taken in the quality control process.

C. Quality audits are usually done by quality assurance department to look for new lesson learn and good practices that the project can contribute.

D. Perform quality assurance process provides a way for continuously process improvement of all the process

Correct Answer: A

Explanation:

Quality assurance works at execution phase, not planning. Quality control measures how long it takes to plan the project or measure other areas of planning performance.

Domain Name: 8. Quality
Reference: PMBOK5 Section 8.2 Page 245

Home     Previous     Next


Disclaimer: Simulationexams.com is not affiliated with any certification vendor, and Sim-Ex™ Practice Exams are written independently by SimulationExams.com and not affiliated or authorized by respective certification providers. Sim-Ex™ is a trade mark of SimulationExams.com or entity representing Simulationexams.com.PMP® is a trademark of PMI™.